  • Scan the QR Code for Helpful Tips when installing your fence.
  • Before driving pipe anchors, check for underground utilities. In the US, call 811 or visit www.call811.com. In Canada, visit www.clickbeforeyoudig.com to find your provincial one-call centre.
  • If your yard slope exceeds 3–4in per 6ft panel, split your panels and add an extra post and brackets.

Returns: Please let us help resolve any issues before initiating a return. If a return is still necessary, it must be initiated with the retailer where the product was purchased.

Need Help or Replacement Parts?

Our US-based customer service team is available Monday–Friday, 9am–5pm EST.

For faster service, have your item number (BL19101) and part name ready. A batch lot number (found on the end of the box) is also helpful — it assists us in identifying and resolving any production issues.

Finishing Post: BL19042

Your panel comes with 1 post/anchor kit. You will need 1 BL19042 to finish the fence run.

If installing a gate, you will need two finishing posts — one to terminate the run and one to support the gate. See the diagram below for reference.

Purchase 1 BL19042 to finish your fence run

Buying Guide

Product Specifications & Dimensions

BL19101 dimensions and specifications

Post Pounder Considerations

Good

Good: Sledgehammer 10-15lbs

Sledgehammer
10-15lbs.
A basic option for very small projects. Requires two people to keep pipes level during installation.

Better

Better: Manual post pounder 12-30lbs

Manual Post Pounder
12-30lbs.
Best for projects with fewer than 10 pipes. Available online or at hardware stores.

Best

Best: Gas powered post pounder

Gas Powered Pounder
Rentals are ideal for larger projects. Significantly reduces time and effort required.

Pounder must have 3in or greater barrel diameter

Note:
Choose a post pounder with a barrel diameter of 3in or greater. Pounder barrel cannot be longer than 24in.

Tip! Don't use a 5lb sledgehammer — it won't generate enough force to be effective, and driving the pipe turns into a slow, frustrating grind.

Required Tools

Pounder / Sledge Hammer

Tool: Pounder or sledge hammer

Drill with 2in Bit

Tool: Drill with 2in bit

Measuring Tape

Tool: Measuring tape

Stringline Reel

Tool: Stringline reel

Stakes (for stringline)

Tool: Stakes for stringline

Hammer / Mallet (for stakes)

Tool: Hammer or mallet for stakes

Pencil

Tool: Pencil

1ft Level

Tool: 1ft level

Large Level

Tool: Large level

Part Identification

A

Pipe Anchor (1)
1⅝in Diameter x 58½in L Part A: Pipe anchor 1⅝in Diameter x 58½in L

B

Post (1)
4in x 4in x 53in Part B: Post 4in x 4in x 53in

C

Top Rail (1)
1½in x 3½in x 67¾in Part C: Top rail 1½in x 3½in x 67¾in, holes both sides

Top rail has holes on both sides

D

Bottom Rail (1)
1½in x 3½in x 67¾in Part D: Bottom rail 1½in x 3½in x 67¾in, holes one side

Bottom rail has holes on only one side

E

Picket (13)
⅞in x 1½in x 44¼in Part E: Picket ⅞in x 1½in x 44¼in

F

Bracket (4) Part F: Bracket quantity 4

G

1in Self-Drilling Stainless Steel Screw (24) Part G: 1in self-drilling stainless steel screw

H

Post Cap (1) Part H: Post cap quantity 1

Practice Makes Perfect

Start with one full panel — it's the best way to learn the process and confirm your spacing before committing. Once the first panel is complete and verified, drive your next pipe anchor and build each remaining panel one at a time.

Build one full panel first before continuing

Important: Before driving pipe anchors, check for underground utilities. In the US, call 811 or visit www.call811.com. In Canada, visit www.clickbeforeyoudig.com to find your provincial one-call centre.

Call 811 before you drive pipe

Step 1: Set Stringline

Hammer a stake at each end of every fence run, then tie string between the stakes. This line keeps your pipes aligned as you drive them. Need help? Watch this video!

Setting stringline stakes along fence run

Step 2: Determine Slope

Check your yard's slope before driving any pipes

Under 3–4in slope per panel: no extra posts required

For a slope of 3–4in or less per 6ft panel, no extra posts are needed. You can trim the top of the post to follow the grade once your panel is built.

Over 3–4in slope per panel: extra post required

For a slope greater than 3–4in per 6ft panel, you will need to split your panel. Purchase an additional post and set of brackets before continuing.

Step 3: Mark Pipe Locations

Mark the ground every 72in to determine exact pipe locations, measuring center-to-center.

Mark pipe locations every 72in center to center

Step 4: Remove Top Donut

Parts Required

A x1

Before driving your pipes, remove the top donut from pipe anchor (A) by pulling the tabs to unlock and lifting the top donut free. Need help? Watch our leveling donut video.

Pull tabs to unlock and lift top donut from pipe anchor

Step 5: Install Pipes

Parts Required

A x1

Drive pipe anchor (A) into the ground at your first marked location, checking for level roughly every 6in. To stay level, pound equally from all four sides. Continue until the lower gear touches the ground. Repeat for the second pipe — center-to-center spacing must be 72in.

Drive pipe anchor into ground, check level every 6in

Step 6: Adjust Donuts to Level

With both pipes in the ground, reinstall the top donut onto each pipe anchor (A) one at a time. Check each pipe for level. If a pipe is slightly off, pull the donut tabs outward and rotate the donut to shift its position and compensate. Refer to the donut leveling video in Step 4 for help.

Reinstall top donut and adjust pipe for level

Rotate donut until pipe anchor A reads level

Step 7: Install Posts

Parts Required

B x1

Slide post (B) down over pipe anchor (A). On flat ground, bury the post 3–4in to avoid a floating look.

Slide post B down over pipe anchor, bury 3–4in

Installing at a non-standard angle? Watch our angle bracket guide before placing your brackets.

Step 8: Install Bottom Bracket (First Post)

Parts Required

F x1 G x4

On your first post, measure 2in up from the bottom of the post and 1⅛in in from the front edge. Mark this position, then align bracket (F) to your mark and secure it using (4) screws (G). This is your bottom rail bracket.

Secure bracket F 2in from post bottom, 1⅛in from edge

Step 9: Align Bottom Bracket (Second Post)

Parts Required

D x1 F x1

Slide one end of the bottom rail (D) into the bracket you just installed. Without driving any screws, loosely place a second bracket (F) over the open end of the rail on the second post. Use a level to confirm the rail is level, then mark the bracket position on the second post. Remove the rail and bracket — do not secure anything yet.

Level rail D to mark second bottom bracket position on post

Step 10: Install Bottom Bracket (Second Post)

Parts Required

F x1 G x4

Using the mark you made in Step 9, align bracket (F) on the second post and secure it with (4) screws (G).

Secure bracket F at marked location with four screws G

Step 11: Install Bottom Rail

Parts Required

D x1 G x4

Slide the bottom rail (D) into both brackets. Once seated, secure the rail to each bracket using (4) screws (G) — (2) per bracket side.

Slide bottom rail D into both brackets, secure with screws G

Step 12: Install Top Bracket (First Post)

Parts Required

F x1 G x4

On your first post, measure 33in up from the top of the bottom rail and mark the position. Align bracket (F) to your mark and secure it to the post using (4) screws (G). This is your top rail bracket.

Secure top bracket F at 33in above bottom rail

Step 13: Align Top Bracket (Second Post)

Parts Required

C x1 F x1

Slide one end of the top rail (C) into the bracket you just installed. Without driving any screws, loosely place a second bracket (F) over the open end of the rail on the second post. Use a level to confirm the rail is level, then mark the bracket position on the second post. Remove the rail and bracket — do not secure anything yet.

Level rail C to mark second top bracket position on post

Step 14: Install Top Bracket (Second Post)

Parts Required

F x1 G x4

Using the mark you made in Step 13, align bracket (F) on the second post and secure it with (4) screws (G).

Secure top bracket F at marked location with four screws G

Step 15: Install Top Rail

Parts Required

C x1 G x4

Slide the top rail (C) into both brackets. Once seated, secure the rail to each bracket using (4) screws (G) — (2) per bracket side.

Slide top rail in and secure with 2 screws on each side

Step 16: Insert Pickets

Parts Required

E x13

Insert all (13) pickets (E) through the top rail, pushing each one firmly down until you hear and feel it lock into the bottom rail. Don't be afraid to use muscle — you will not break the vinyl.

Push pickets E through top rail to lock into bottom rail

Step 17: Install Post Cap

Parts Required

H x1

Press the post cap (H) firmly onto the top of your post until it is fully seated.

Press post cap H firmly onto your post until fully seated